WORK

LIST OF WORKS COMPLETED (BOT PROJECTS)

  

No

Name of Project

Employer

Project Cost (Rs. in Lacs)

Year of completion of construction

Time allowed for completion

Actual time taken & % Time taken

1

Mhow-Ghattabillod Road SH-27

MD MPSIDC Bhopal

1800.00

2000

12 Months

206 Day

 

56.44%

2

Construction of Mandsaur Bypass Road

EE PWD Mandsaur

900.00

1998

24 Months

371 Days

 

50.82 %

3

Construction of New Road of Katni Bypass Katni

EE PWD Katni

600.00

2001

30 Months

580 Days

 

63.73 %

4

Champa – Jharia Bridge

EE PWD Bilaspur (CG)

35.00

1996

4 Months

56 Days

 

46.67 %

    


LIST OF WORKS COMPLETED (CONSTRUCTION PROJECTS)

No

Name of Project

Employer

Project Cost (Rs. in Lacs)

Year of completion of construction

Time allowed for completion

1

Asphalting of road Indore Airport to Industrial Area Pithampur

MD, MPAKVN, Indore (M.P.)

263.27

2004

6 Months

2

IRQP work of Sehore Dewas Road

Strengthening with BM, SDBC and Paved Shoulder

MPRSNNL

AVN Towers

M.P. Nagar

Bhopal (M.P.)

2290.00

2003

8 Months

3

Inner Ring Road, Ujjain - Const./Strengthening of ring road incl. Earthwork, GSB, WBM, BM, MSS, SDBC, Concreting (PQCC), Culverts etc

EE PWD Div. II Ujjain (M.P.)

932.00

2003

15 Months

4

Construction of WBM road from Indore Airport to Pithampur

MD, MPAKVN, Indore (M.P.)

254.00

2003

6  Months

5

Asphalting of Existing BT Road Industrial Area I, II & III Pithampur

MD, MPAKVN, Indore (M.P.)

122.39

2003

4 Months

6

Upgrading & Strengthening of existing roads Industrial Area Pologround, Indore

MD, MPAKVN, Indore (M.P.)

115.04

2003

8 Months

7

Improvement work of Suwasara Garoth Road under Mandi Funds Package No.31/2

EE PWD, Mandsaur

216.73

2002

11  Months


LIST OF WORKS COMPLETED (CONSTRUCTION PROJECTS) – PRIVATE COMPANIES

S.No.

Name of Project

Project Cost (Rs. In Lacs)

1

Construction of road for Indorama Synthetics Ltd., Pithampur

105.00 Lacs

2

Construction of road for L&T ECC Construction Group, Pithampur

90.00 Lacs

3

Construction of road for Nirma Soap Ltd., Pithampur

80.00 Lacs

4

Construction of road for National Steel, Ghattabillod

60.00 Lacs

5

Construction of road for Kinetic Honda Motors Ltd., Pithampur

30.00 Lacs

6

Construction of road for Agrawal Public School, Indore

27.31 Lacs

7

Construction of road for Eicher Motors Ltd., Pithampur

20.00 Lacs

8

Construction of road for Chameli Devi Public School, Indore

18.50 Lacs

LIST OF WORKS IN HAND

S. No.

Project Name

Employer

Project Cost (Rs. In Crores)

State

1

Construction of Rewa Bypass under BOT Scheme

PWD, Rewa (M.P.)

48.00

Madhya Pradesh

2

Construction of ROB on MR – 10, Indore (M.P.) under BOT Scheme

Indore Development Authority, Indore (M.P.)

14.76

Madhya Pradesh

3

Ratanpur–Himatnagar

NHAI, Himmatnagar (Guj.)

1.24

Gujarat

4

Ajmer to Bhilwara

NHAI, Kishangarh (Raj.)

4.43

Rajasthan

5

Bhilwara to Chittorgarh

NHAI, Kishangarh (Raj.)

3.65

Rajasthan

WORKS IN HAND OF GROUP COMPANIES

TAR Infrastructure Ltd.

S.No.

Project Name

Employer

Project Cost (Rs. In Crores)

1

Strengthening of Banswara – Aspur Portion (73.5 Kms.) of Banswara – Udaipur Road (SH – 32) under BOT Scheme.

PWD, Banswara (Raj.)

 

 

 