Completed Projects

Sr. No. Document Tittle Name of Authority Location Date of Completion
1 Widening & Reconstructiuon Of Khamariya-Sultanpur-Nakhtra Road under regular contract Project Pakage-3 MPRDC Khamariya (M.P.) Jul-12
2 Construction of Mandsaur Bypass Road MPPWD Mandsaur (Madhya Pradesh) Jul-98
3 Vatanda Toll Plaza, Toll Collection Ratanpur- Himmatnagar (NH-8) NHAI Vantada (Gujrat) Mar-12
4 Construction of Link Road at Indore IDA Indore (MP) Jul-11
5 Strengthening, Widening and Operating Mhow-Ghatabillod Road on BOT Basis. MPSIDCL Mhow (MP) Jun-01
6 Construction of ROB at Chainage 91.62 & 96.87 on Lebad-Jaora Road Project PanIndia Infrastructure Pvt. Ltd. Ratlam (MP) Jun-11
7 Badwaha- Dhamnod Road, Khalghat-Manawar Road & Khalghat-Kasrawad Road Project Package 4 MPRDC Badwaha (M.P) May-10
8 Strengthening & Widening of Existing 2-Lane Road to 4-Lane from Km. 12.600 to Km 84.700 Indore-Khalghat Section (NH-3) Leighten Contractors India Pvt. Ltd. & OSE Pvt. Ltd. (JV) Khalghat (MP) Jun-10
9 Operation and Maintenance including Strenghtening and Widening of Kondali Talegaon Section (NH-6) NHAI Nagpur (Maharashtra) Jul-08
10 Contruction of Rewa Bypass Road from Km 229/2 to 243/6 of NH-7 on BOT Basis MPPWD-NH Rewa (MP) Aug-08
11 Construction of ROB at MR-10, Indore (M.P) under BOT Basis. IDA Indore (MP) Mar-07
12 Strenthening with BM, SDBC, and Paved Shoulder on Sehore-Dewas Road MPRSNNLA Sehore (MP) May-04
13 Construction of New Katni Bypass MPPWD Katni (MP) Aug-03
14 Widening & Strengthening of 123 Km Road, Bridges, Culverts Etc Ujjain-Jhalawar Road Project MPRSNNLA Ujjain (MP) May-05